模糊综合评判法在隧道岩体含水性预报中的应用
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
为了综合利用各种超前地质预报方法,得出一个相对正确的结论,提出应用模糊综合评判法进行超前地质预报。结合工程实例,从建立评判集、因素集、求取各因素的相对权重等方面介绍模糊综合评判法在超前地质预报中的应用。通过工程实际应用,证明该方法是可行的。
It is recommended that comprehensive fuzzy evaluation method should be used in the geology forecast of tunnel works so as to make full use of all kinds of geology forecast methods and draw a relatively correct conclusion.The application of comprehensive fuzzy evaluation method in the geology forecast of tunnel works is presented in terms of the establishment of the factor set and evaluation set and the obtaining of the relative weight of the various factors on basis of engineering cases.The engineering practice verifies that the evaluation method is feasible.
引文
[1]薛翊国,李术才,李树忱.高风险隧道施工期水害预报方法研究[J].黑龙江水专学报,2008,35(2):117-122.
    [2]赵永贵.国内外隧道超前预报技术评析与推介[J].地球物理学进展,2007,22(4):1344-1352.
    [3]李术才,李树忱,张庆松,等.岩溶裂隙水与不良地质情况超前预报研究[J].岩石力学与工程学报,2007,26(2):217-224.
    [4]刘斌,李术才,张庆松,等.隧道地质灾害预警体系中岩溶裂隙水综合预报技术研究[J].山东人学学报:工学版,2009,39(3):115-121.
    [5]刘浩杰.宜万铁路隧道工程岩溶超前预报的地质分析方法研究[D].北京:北京交通大学,2006.
    [6]朱劲.超前地质预报新技术在铜锣山隧道的应用及综合分析研究[D].成都:成都理工大学,2007.
    [7]李鸿吉.模糊数学基础及实用算法[M].北京:科学出版社,2005.
    [8]吕国英,李茹.基于层次分析法的专家系统开发平台测评指标权集[J].广西师范大学学报:自然科学版,2007,25(4):63-66.
    [9]许树柏.层次分析法原理[M].天津:天津大学出版社,1988.
    [10]李天斌,孟陆波,朱劲,等.隧道超前地质预报综合分析方法[J].岩石力学与工程学报,2009,28(12):2429-2436.
    [11]赵宇.GPR及TSP在隧道超前地质预报中的解泽标志研究[D].成都:成都理工大学,2009.
    [12]藏传伟,黄建华,黄宏伟.TSP地震波波速与隧道围岩类别关系探讨[J].福建工程学院学报,2005,3(6):637-640.
    [13]王齐仁.隧道地质灾害超前探测方法研究[D].长沙:中南大学,2007.
    [14]肖宏跃,雷宛,杨威.地质雷达特征图像与典型地质现象的对应关系[J].煤田地质与勘探,2008,36(4):57-61.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心