基于仿真技术的水利工程项目进度与费用的风险评价
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
讨论水利工程建设项目进度和费用的风险,建立了基于三角分布的网络计划进度和费用风险评价的随机模拟模型.通过统计分析得到进度和费用的模拟概率分布,进而得到进度和费用风险曲线,为评价工程项目的风险提供了依据.最后,对东深供水改造工程某抽水泵站施工网络计划进行模拟,给出其进度和费用的风险分布.
The schedule and cost risks of water resources projects are discussed, and a stochastic simulation model for risk evaluation of network schedule and cost is established based on the triangular distribution. The probability distribution and risk curve of schedule and cost are obtained by statistic analysis, providing a basis for risk evaluation of engineering projects. Finally, the model is applied to the simulation of the construction network schedule for a pumping station in Dongshen water supply reformation project, and the schedule and cost risk distributions are also given.
引文
[1]王卓甫.水利水电施工进度计划的风险分析[J].河海大学学报(自然科学版),1999,27(4):83—87.
    [2]徐哲,冯允成.网络计划进度的风险分析[J].系统工程理论与实践,1998,(4):24—28.
    [3]李干生,王卓甫,白宏坤.网络计划计算机仿真与风险分析[J].河海大学学报(自然科学版),2001,29(1):65—69.
    [4]钱颂迪.运筹学[M].北京:清华大学出版社,1998.288—309.
    [5]中国建筑学会建筑统筹管理研究会.中国网络计划技术大全[M].北京:地震出版社,1993.807—812.
    [6]王卓甫,杨志勇,杨建基.水利水电工程施工进度风险规定下的投资优化[J].河海大学学报(自然科学版),2000,28(6):52—55.
    [7]方再根.计算机模拟和蒙特卡罗方法[M].北京:北京工业学院出版社,1988.1—120.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心