水利水电施工进度问题研究综述
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
综述国内外水利水电施工进度优化和不确定性研究的现状 ;指出在考虑施工活动持续时间不确定的条件下 ,开展施工网络进度计划和优化研究 ,具有实际意义 ;在水利水电施工进度风险一定的条件下 ,尽可能推迟每一工作的开始时间 ,对节省工程投资或成本具有好的效果
The current research on optimization and uncertainty of construction schedule for hydropower projects is reviewed in this paper. The research on risks and optimization of the construction network program is of significance when the lasting time of the construction is uncertain. It is also pointed out that postponing the beginning of projects as later as possible may help save project investments or costs if the risks of the construction progresses are known.
引文
[1]JamesMAntill,RonaldWWoodhead .Criticalpathmethodsinconstructionpractice [M ].NewYork :AWiley IntersciencePublication ,1982 .
    [2 ]DavisEW .Projectschedulingunderresourceconstraintshistoricalreviewandcategorizationofprocedures[J].AIIETrans,1973,5 (4 ) :2 97~ 312 .
    [3]DoerschRH ,PattersonJP .Schedulingprojecttomaximizeitspresentvalue [J ].AZero OneProgrammingApproach ,ManagementScience,1977,2 3:882~ 889.
    [4 ]MorseL ,WhitehouseG .Astudyofcombiningheuristicsforschedulingprojectswithlimitedmultipleresources[J].CompAndIndustrialEngrg ,1988,15 (4 ) :15 3~ 16 1.
    [5 ]TsaiDM ,ChiuHN .Twoheuristicforschedulingmultipleprojectswithresourceconstraints [J].ConsMgmtAndEconomics,1996 ,14:32 5~ 340 .
    [6 ]ElsayedEA ,NasrNI.Heuristicsforresource constrainedscheduling[J].InternationalJournalofPublicationResearch ,1986 ,2 4(2 ) :12 4~ 132 .
    [7]刘明 ,吴唤群 .资源有限———工期最短的分枝定界算法[J].系统工程 ,1999,92 (2 ) :72~ 75 .
    [8]HarrisRB .Precedenceandarrownetworkingtechniqueforconstruction[M].NewYork :Wiley ,1978.
    [9]高明生 ,何建敏 .单步比较法———网络计划中的一种优化方法 [J],管理工程学报 ,1999,13(3) :5 7~ 5 8.
    [10 ]戴建国 .活动网络资源均衡问题及其遗传算法 [J].系统工程理论与实践 ,1996 (2 ) :2 9~ 36 .
    [11]GoldbergDE .Geneticalgorithmsinsearch ,optimization ,andmachinelearning[J].Addison WesleyPublishingCompanyInc,1989.
    [12 ]MeyerWL ,ShafferLR .ExtendingCPMformultiformprojecttime costcurves[J].JournalofConstructionEngineeringandManagement,1990 ,91(1) :45~ 6 7.
    [13]TalbotFB .Resource constrainedprojectschedulingwithtime resourcetradeoffs:thenon preemptivecase[J].MgmtSci,1982 ,2 8(5 ) :1197~ 12 10 .
    [14]PanagiotakopoulosD .Cost timemodelforlargeCPMprojectnetworks [J].JournalofConstructionEngineeringandManagement,1977,10 3(2 ) :2 0 1~ 2 11.
    [15 ]PattersonJH ,TalbotFB ,SlowinskiR ,WeglarzJ.Computationalexperiencewithabacktrackingalgorithmforsolvingageneralclassofprecedenceandresourceconstrainedschedulingproblem [J].EuropeanJournalofOperationalResearch ,1990 ,49:6 8~ 79.
    [16 ]SungCS ,LimSK .AProjectactivityschedulingproblemwithnetpresentvaluemeasure [J].InternationalJournalofProductionEconomics ,1994,37:177~ 187.
    [17]ChanWT ,ChuaDKH ,KannanG .Constructionresourceschedulingwithgeneticalgorithms[J].JournalofConstructionEngineeringandManagement,1996 ,12 2 (2 ) :12 5~ 132 .
    [18]吴之明 .网络进度费用的联合管理 [J].系统工程理论与实践 ,1995 (6 ) :10~ 17.
    [19]Sou SenLeu ,Chung HueiYang.GA basedmulti criteriaoptimalmodelforconstructionscheduling [J].JournalofConstructionEngineeringandManagement,1999,12 5 (6 ) :42 0~ 42 6 .
    [2 0 ]MulhollandB ,ChristianJ .Riskassessmentinconstructionschedules [J].JournalofConstructionEngineeringAndManagement,1999,12 5 (1) :8~ 15 .
    [2 1]ShouQing ,RobertLKTiong ,SengKiongTing ,DavidAshley.Politicalrisks :analysisofkeycontractclausesinChina’sproject [J].JournalofConstructionEngineeringandManagement,1999,12 5 (3) :190~ 197.
    [2 2 ]HerbertMoskwitz,DerekBurn .Decisionandriskanalysis[J].EuropeanJournalofOperationalResearch ,1987,2 8:2 47~2 6 0 .
    [2 3]ThompsonP ,PerryJ .Engineeringconstructionrisk :aguidetoprojectriskanalysisandriskmanagement[M ].London :ThomasTelford ,1992 .
    [2 4]潘宝根 .计划协调技术 [A].李庆华 .中国网络计划大全[C].北京 :地震出版社 ,1993 .80 7~ 812 .
    [2 5 ]LittlefieldTK ,RandolphPH .Reply—ananswertosasieni’squstiononPERTtimes[J].MgmtSci,1987,33(10 ) :135 7~135 9.
    [2 6 ]MacCrimmonKR ,RyavecCA .AnanalyticalstudyofthePERTassumption[J].OpnsRes ,196 4(12 ) :6~ 7.
    [2 7]李干生 ,王卓甫 ,白宏坤 .网络计划计算机仿真与风险分析 [J].河海大学学报 ,2 0 0 1,2 9(1) :6 5~ 6 9.
    [2 8]BajisDodin .DeterminingthekmostcriticalpathsinPERTnet works[J].OpnsRes,1984,32 (4 ) :85 9~ 877.
    [2 9]BajisDodin .BoundingtheprojectcompletiontimedistributioninPERTnetwork[J].OpnsRes,1985 ,33(4 ) :86 2~ 881.
    [30 ]Al bahar.Systematicriskmanagementapproachforconstructionproject[J].JournalofConstructionEngineeringandManagement,1990 ,116 (4 ) :5 33~ 5 46 .
    [31]徐哲 ,冯允成 .网络计划的风险分析 [J].系统工程理论与实践 ,1998(4 ) :2 5~ 2 8.
    [32 ]王卓甫 ,陈登星 .水利水电施工进度计划的风险分析[J].河海大学学报 ,1999,2 7(4 ) :83~ 87.
    [33]DiderDubois,HenriPrade .OperationsonfuzzynumbersInternat[J].JSystemsSci,1987,9(6 ) :6 13~ 6 2 6 .
    [34]周长春 .非确定时间参数网络规划的一种新算法 [J].系统工程理论与实践 ,1998(5 ) :89~ 91.
    [35 ]NasutionSH .Fuzzycriticalpathmethod[J].IEEETransactiononSMC ,1994,2 4(1) :48~ 5 7.
    [36 ]ChangIS ,TsujimuraY .Anefficientapproachforlargescaleprojectplanningbasedonfuzzydelphimethod[J].FSS ,1995 ,76 (3) :2 77~ 2 88.
    [37]胡劲松 ,达庆利 .单代号模糊网络的关键路线分析 [J].系统工程理论与实践 ,1998(8) :10 8~ 112 .

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心