下坂地沥青混凝土心墙坝动力反应分析
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
下坂地水库地处高地震区,大坝基础覆盖层厚度达150 m,且存在粉细砂层,针对下坂地大坝工程的特点,在坝料静、动力特性试验和三维静力分析的基础上,采用考虑坝体—覆盖层—防渗体等动力相互作用的非线性有效应力地震反应分析方法,对下坂地沥青混凝土心墙坝坝体和覆盖层进行了地震情况下安全评价。
Xiabandi Reservoir is located in a high seismic zone,the covering thickness of the dam foundation reaches to 150 m,and there exists a fine sand layer.Directing against the characteristics of the dam,and based on the static and dynamic tests of the materials of the dam and the three-dimensional static analysis,the security of the dam and cover in circumstances of earthquake are evaluated by adopting the nonlinear and effective stress analysis of considering the dynamic interreaction of dam-cover-cut off wall.
引文
[1]SL203-97.水工建筑物抗震设计规范[S].北京:中国水利水电出版社,1997.
    [2]水利部西北水利科学研究所.下坂地水利枢纽工程粗砾料大型静三轴试验[R].杨凌:水利部西北水利科学研究所,2002.
    [3]中国水利水电科学研究院.新疆下板地水库坝料动力特性试验研究报告[R].北京:中国水利水电科学研究院,2004.
    [4]赵剑明,等.面板坝三维非线性动力分析研究.“九五”国家重点科技攻关子题(96-221-02-03-02)报告[R].北京:中国水利水电科学研究院,2000.
    [5]赵剑明,汪闻韶,张崇文.土石坝振动孔压影响因素的研究[J].水利学报,2000,31(5):54-59.
    [6]顾淦臣.土石坝地震工程[M].南京:河海大学出版社,1989.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心