不同坝址方案下某堆积体变形稳定分析
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
基于FLAC3D有限差分法,对某堆石坝坝址右岸坝前的一堆积体在不同坝址方案、不同工况下的变形以及应力和塑性区的分布进行了三维数值模拟研究。根据研究结果,建议采用上部削坡和开挖范围内浆砌石方案护坡;考虑到建坝调水工程、引水线路、坝体施工工程量及坝库区边坡稳定等问题,建议将坝体布置在中坝址。
The three-dimensional distributions of deformation,stress and plastic region of a right-bank accumulation body in front of a rock-fill dam under different dam site selection plans and working conditions are simulated by using finite difference method of FLAC3D.Based on the simulation results,it is recommended that the upper part of slope is unloaded and the masonry is used to support the slope in excavation area,and the dam is arranged in middle site after taking into account the water transfer project,water diversion route,construction quantities of dam and the stability of slopes in reservoir area.
引文
[1]寇晓东,周维垣,杨若琼.FLAC3D进行三峡船闸高边坡稳定分析[J].岩石力学与工程学报,2001,2(1):6-10.
    [2]张卓,练继建,杨晓慧,等.岩质边坡在降雨条件下的稳定性分析[J].哈尔滨工业大学学报,2009,41(10):202-205.
    [3]黄宜胜,李建林.董箐水电站溢洪道泄槽段边坡三维有限元分析[J].水电能源科学,2010,28(12):85-88,109.
    [4]陈昌凯,阮永芬,熊恩来.地震作用下边坡稳定的动力分析方法[J].地下空间与工程学报,2005,1(7):1054-1057.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心