含有最大时距的搭接网络计算方法研究
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
实际工程项目中,工作之间的关系多为搭接关系,时距可能为最大时距,其计算过程也更为复杂。为了减少程序计算搭接网络时间参数和关键线路的所需时间,将网络中FTF,STS,STF,FTS这4种简单逻辑关系以及2种常见的FTF&STS和STF&FTS组合逻辑关系全部转化为FTS逻辑关系,引入虚拟时距工作的概念,将搭接网络转化为传统的衔接网络。并采用衔接网络的时间参数计算公式和最大时距的检验法则,得出转化后的衔接网络的时间参数,所得的各实工作的时间参数值和关键线路与用一般方法直接计算出的结果一致。基于这种新的算法编制计算CPM分析程序进行PERT分析时,将会缩短其计算时间,提高决策效率。
There are many concurrent activities with maximum time lags practically and its calculating process is more complex.In order to reduce the calculation time,a new approach is presented.The logic relations of FTF,STS,STF,FTS,FTF&STS,and STF&FTS are tranformed into FTS by introducing a dummy time lag activity so that multi-dependency network is converted to traditional network.Time parameters are obtained by the equations of schedule calculations for the conventional network and check rules for the maximum time lags.Time parameters and critical paths are the same as the results by equations of schedule calculations for the traditional network.Based on the approach,computer programs are made to identify the critical path.
引文
[1]孙震,穆静波.土木工程施工[M].人民交通出版社,2004.
    [2]Clifford J.Schexnayder,Richard E.Mayo.ConstructionManagement Fundamentals[M].重庆:重庆大学出版社,2005.
    [3]佟鹤晶,乞建勋.搭接网络向双代号网络的转化[J].技术经济2009,28(10):125-128.
    [4]杨冰.网络计划计算模型的统一[J].系统工程理论与实践2002,3(3):51-55.
    [5]李万庆,孟文清.工程网络计划技术[M].科学出版社,2009.
    [6]梁绍周.搭接网络计划方法[G].见(In):中国建筑学会建筑统筹管理研究会.中国网络计划技术大全.北京:地震出版社,1993.
    [7]成虎,刘训良.单代号搭接网络中时距MA定义及算法[J].建设管理现代化,1994(1):14-15.
    [8]张厚川.搭接网络计划的简化计算方法[G].见(In):中国建筑学会建筑统筹管理研究会.中国网络计划技术大全.北京:地震出版社,1993.
    [9]王卓甫.工程进度风险计算研究[D].南京:河海大学,2002.
    [10]廖钰.搭接网络中关键链的识别方法[D].武汉:华中科技大学,2007.
    [11]佟鹤晶.搭接网络中特异活动对时间费用影响研究[D].北京:华北电力大学,2009.
    [12]张照煌,梁会森.搭接网络计划工作总时差计算方法[J].应用基础与工程科学学报,2009,11(17):151-157.
    [13]成虎.工程项目管理(第二版)[M].北京:中国建筑工业出版社,2001.
    [14]中国建筑学会建筑统筹管理分会.JGJ/T121-99工程网络计划技术规程[S].北京:中国建筑工业出版社,1999.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心