大型高耸建筑集合群体的拆除爆破技术及应用
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
采用预处理的办法将某大型水泥厂旧厂房分割成3组独立的结构群体,分组顺序延时起爆,向3个方向倾倒的“同一建筑异向倾倒方案”,并同时采用分组延时爆破、铺设减震垫层和开挖减震沟,显著降低了触地爆破震动,达到预期目的。
Some pre-treatment measures are used in a large cement factory building such as dividing them into 3 separated structures and priming them in sequence,so three different directional collapsing of the same construction is realized.In addition,the ground vibration resulted from the collapsing of the interconnected silos can be reduced remarkably by using the delay blasting,laying a vibration damped pad and excavating a vibration_separated ditch.The desired blasting results were achieved.
引文
[1]冯叔瑜,吕毅,杨杰昌,等.城市控制爆破[M].北京:中国铁道出版社,1996.
    [2]陈寿如,周治国,宋光明.特殊框架拆除爆破的几点体会[J].西部探矿工程,1998,10(5):53-54.
    [3]史秀志,陈寿如,宋光明,等.倒塌空间不足的水塔爆破拆除[J].爆破器材,2001,30(3):23-25.
    [4]中华人民共和国国家质量监督检验检疫总局.GB 6722-2003爆破安全规程[S].北京:中国标准出版社,2004.
    [5]马建军,钟冬望,杨军,等.大型筒仓的机械与爆破综合控制拆除技术[J].武汉科技大学学报,2000,(4).
    [6]秦明武.控制爆破[M].北京:冶金工业出版社,1993.
    [7]赵福兴.控制爆破工程学[M].西安:西安交通大学出版社,1988.
    [8]刘殿中.工程爆破实用手册[M].北京:冶金工业出版社,1999.
    [9]张奇.拆除爆破防护问题的研究[J].爆破,1995,(2).

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心