汶川特大地震灾后重建工程工期影响因素分析
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
从灾后重建工程的建设规模、投资金额、延续周期及项目类型等四个方面,探究灾后重建工程进度的系统性、紧迫性、动态性和阶段性等工程进度特征;依据多国建设工期影响因素的比较分析结论,探讨对汶川特大地震灾后重建工程工期影响因素,其结果表明:工期主要影响因素是资金、物资、环境、管理;并对灾后重建工程的进度管理提出相应措施建议,以期为重建建设工程的实践提供一些参考。
This paper explores the systematicness,priority,dynamicity and periodicity of post-Wenchuan earthquake reconstruction in terms of the scope,investment,schedule and project type.A review of the literature from different countries is conducted for a diagnosis of the factors affecting reconstruction duration.This study shows that finance,materials,environment and management are the four most important factors influencing the reconstruction duration.Based on the analysis results,this paper provides suggestions for future reconstruction schedule management.
引文
[1]Walker D H T.An investigation into construction time performance[J].Construction Management and Economics,1995,13(3):263~274
    [2]Chan A P C,Scott D,Chan A P L.Factors affecting the success of aconstruction project[J].Journal of Construction Engineering andManagement,2004,130(1):153~155
    [3]Bromilow F G.Contract time performance expectations and the reality[J].Building Forum,1969,1(3):70~80
    [4]Ireland V B E.The role of managerial actions in the cost,time andquality performance of high rise commercial building projects[J].Construction Management and Economics 1985,3(1):59~87
    [5]Nkado R N.Construction time-influencing factors:the contractor sperspective[J].Construction Management and Economics,1995,13(1):81~89
    [6]Chan D W M,Kumaraswamy M M.Compressing construction dura-tions:lessons learned from Hong Kong building projects[J].Interna-tional Journal of Project Management,2002,20(1):23~35
    [7]Praveen S,Mehmet E B,Taehoon H,et al.Model for analysis of factorsaffecting construction schedule in highway work zones[J].Journal ofConstruction Engineering and Management 2006,132(6):508~517
    [8]王兴元,赵铁生.大型火电项目建设工期影响因素分析评价研究[J].基建优化,1991,12(4):41~47
    [9]石勇民,胡浩.公路建设BOT项目关键因素分析[J].长安大学学报(社会科学版),2002,4(2):53~56
    [10]黄定轩,尤建新,杜波.不同结局建筑施工项目关键因素实证分析[J].土木工程学报,2006,39(12):112~118
    [11]中华人民共和国建设部.全国统一建筑安装工程工期定额[S].2000-04
    [12]Chan D W M.Modelling construction durations for public housingprojects in Hong Kong[D].PHD thesis,the University of HongKong,1998
    [13]Baldwin J R,Manthei J M,Rothbart H,et al.Causes of delay in theconstruction industry[J].Journal of Construction Division,1971,97(2):177~187
    [14]NEDO.Faster building for industry[R].Millbank,London,(UK),National Economic Development Office(NEDO),1983
    [15]Chalabi F A,Camp D.Causes of delay and overruns of constructionprojects in developing countries[C].Proceedings of the Fourth In-ternational Symposium on Organization and Management of Construc-tion:Developing Countries,Waterloo Canada 1984,3(10):723~734
    [16]Arditi D,Akan G T,Gurdamar S.Reasons for delays in public pro-jects in Turkey[J].Construction Management and Economics,1985,3(2):171~181
    [17]NEDO.Faster building for commerce[R].Millbank,London,(UK),National Economic Development Office(NEDO),1988
    [18]Okpala D C,Aniekwu A N.Causes of high costs of construction inNigeria[J].Journal of Construction Engineering and Management,1988,114(2):233~244
    [19]Naoum S G.Procurement and project performance-a comparison ofmanagement contracting and traditional contracting[C].Ascot,UK:The Chartered Institute of Building(CIOB),1991
    [20]Mansfield N R,Ugwu O O,Doran T.Causea of delay and cost over-runs in Nigerian construction projects[J].International Journal ofProject Management,1994,12(4):254~260
    [21]Assaf S A,Al-Khalil M,Al-Hazmi M.Causes of delay in largebuilding construction projects[J].Journal of Management in Engi-neering,1995,11(2):45~50
    [22]Chan D W M,Kumaraswamy MM.A comparative study of causes oftime overruns in Hong Kong construction projects[J].InternationalJournal of Project Management,1997,15(1):55~63
    [23]Sambasivan M,Soon Y W.Causes and effects of delays in Malaysianconstruction industry[J].International Journal of Project Manage-ment,2007,25(5):517~526
    [24]Hubbard D G.Successful utility project management from lessonslearned[J].Project management Journal,1990,21(3):19~23
    [25](美)弗雷德里克E.古尔德,南希E.乔伊斯.工程项目管理[M].孟宪海,译.北京:清华大学出版社,2006
    [26]徐玖平,卢毅.地震灾后重建系统工程的综合集成模式[J].系统工程理论与实践,2008,28(7):1~16
    [27]李跃宇,徐玖平.项目时间管理[M].北京:经济管理出版社,2008

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心