芦山“4·20”地震后宝兴县城打水沟泥石流发育趋势及防治方案
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
打水沟为宝兴河右岸的一级支流,位于宝兴县城城区,流域面积1.01 km2,主沟长度1.85 km,主沟比降640‰。受芦山"4·20"地震的影响,流域中下游直接引发了大量的崩滑体,加之地形陡峻,且位于青衣江-鹿头山暴雨区边缘,极容易发生泥石流。一旦发生泥石流,将会对沟口建筑和人员的安全造成巨大危害。通过对打水沟地震前后遥感影像的解译,结合野外考察,综合判定该沟为地震触发的潜在性泥石流沟。进一步分析估算,由于地震震动导致流域内发育6处崩塌体,总面积20 375 m2,松散固体物质总量为15.20×104m3。在分析泥石流形成条件与发展趋势的基础上,提出了打水沟泥石流减灾方案,并对泥石流排导槽梯形最佳过流横断面进行了设计。通过计算分析得到,在排泄设计标准的泥石流时,排导槽的最佳过流断面宽度为2.38 m,深度为2.23 m。
The Dashui gully is a right-bank branch of the Baoxing River,located in Baoxing County,one of the areas most affected by the Lushan"4·20"Earthquake,Sichuan,China.The gully has a basin area of 1.01 km2,is 1.85 km long,and the gully's longitudinal slope is 640 ‰.The gully was lack of sediment supply conditions before the earthquake.After earthquake,6 landslides varying in size were induced by the earthquake and distributed in the middle and lower reaches.Together with the steep high landform conditions and favorable rainfall conditions,debris flow will be easy to form and cause great damages to buildings and human lives at the outlet area.Based the satellite images interpretation before and after the earthquake and the filed investigation,the loose solid materials,catchment integrated coefficient,relative cutting degree,mean channel gradient,mean hillside gradient and stratum lithology were selected as identification factors.Then,the Dashui Gully was identified as an earthquake-induced potential debris flow torrent.The 6 landslide induced by the earthquake cover an area of 20 375 m2with a total volume of 15.20 × 104m3.Based on the formation conditions and potential tendency,the debris flow mitigation measure was proposed and the optimal cross-section design for the trapezoid shaped debris flow drainage canal of the gully is discussed.After calculation,the width and depth of the optimal trapezoid shaped debris flow drainage canal were equal to 2.38 m and 2.23 m respectively for draining the debris flow of 50 years return period.
引文
[1]Li Yong,Huang Runqiu,Zhou Rongjun,et al.Geological Background of Longmen Shan Seismic Belt and surface ruptures in Wenchuan earthquake[J].Journal of Engineering Geology,2009,17(1):3-18[李勇,黄润秋,周荣军,等.龙门山地震带的地质背景与汶川地震的地表破裂[J].工程地质学报,2009,17(1):3-18]
    [2]Tang C,Zhu J,Ding J,et al.Catastrophic debris flows triggered by a 14 August 2010 rainfall at the epicentre of the Wenchuan earthquake[J].Landslides 2011,8:485-497
    [3]Lin C W.Impact of Chi-Chi earthquake on the occurrence of landslides and debris flows:example from the Chenyulan River watershed,Nantou,Taiwan[J].Engineering Geology,2003,(71):49-61
    [4]Tang Chuan,Liang Jingtao.Characteristics of debris flows in Beichuan epicenter of the Wenchuan earthquake triggered by rainstorm on September 24,2008[J].Journal of Engineering Geology,2008,16(6):751-758[唐川,梁京涛.汶川震区北川9.24暴雨泥石流特征研究[J].工程地质学报,2008,16(6):751-758]
    [5]Zhou Bifan,Li Deji,Luo Defu,et al.Guide to prevention of debris flow[M].Beijing:Science Press,1991:125-129[周必凡,李德基,罗德富,等.泥石流防治指南[M].北京:科学出版社,1991:125-129]
    [6]You Yong,Liu Jinfeng,Chen Xingzhang.A convenient designation for the optimal hydraulic cross-section of“Rectangle-V”shaped drainage canal of viscous debris flow[G]//Harold Annegarn,IGARSS 2009-International Geoscience and Remote Sensing Symposium,Cape Town,South Africa,07-2009,II392-395.
    [7]You Yong.Optimal hydraulic condition of debris flow drainage canal[J].Journal of Mountain Science,1999,17(3):255-258[游勇.泥石流排导槽水力最佳断面[J].山地学报,1999,17(3):255-258]
    [8]You Yong,Liu Jinfeng.Comparison of hydraulics conditions among usual debris flow drainage canal[J].Chinese Journal of Rock Mechanics and Engineering,2006,25(Suppl.1):2820–2825[游勇,柳金峰,欧国强.泥石流常用排导槽水力条件的比较[J].岩石力学与工程学报,2006,25(Suppl.1):2820-2825]
    [9]Yong You,Jinfeng Liu,Xingzhang Chen.Debris flow formation conditions and optimal characteristics of drainage canal following Wenchuan earthquake[J].Environmental Earth Sciences,2012,65(4):1005-1012

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心