摘要
本文提出我国北方含水量高的低洼地段公路工程中路基填方铺设方法,重点研究了材料配合比不确定、工程地质条件复杂、充填施工质量不易控制等问题,进行二灰土击实与压缩性能的试验研究,得出了石灰、粉煤灰和土3种充填材料的配合比,并针对工程特点,提出了确保施工质量的措施。室内试验及现场施工均取得了较满意的结果,该研究为公路路基填方提供了可借鉴的经验。
In order to reduce the uncertainty of the proper proportion among lime,fly ash and soil in the mixture design,and overcome the difficulties in quality control in the complex geological condition for road engineering,the mixture design and the filling method of road base in low-lying area with much water in north China were introduced.Then,the compressing test was conducted and the proper proportion was given.Finally,some measures to controll the quality of fill were proposed.Test results and the application in construction show that the mixture design and the quality control measures were proper.
引文
[1]Arora Sunil1,Aydilek Ahmet H.Class F fly-ash-amended soils as highway base materials[J].Journal of Materials in Civil Engineering,2005,6(17):640-649.
    [2]Davidson D T,Handy R L.Soil stabilization:highway-engineering handbook[M].McGraw-Hill Publishing Company,Inc.,1960.
    [3]JTJ034-2000,公路路面基层施工技术规范,中华人民共和国行业标准[S].北京,人民交通出版社,2000.
    [4]徐培华,王安玲.公路工程混合料配比设计与试验技术手册[M].北京:人民交通出版社,2001.
    [5]何杨,栾茂田,许成顺,等.复杂应力条件下松砂振动孔隙水压力与体变特性的试验研究[J].地震工程与工程振动,2005,25(6):127-134.
    [6]Chang Pingkun.An approach to optimizing mix design for properties of high-performance concrete[J].Cement&Concrete Research,2004,4(34):623-629.
    [7]王兰民,袁中夏,王峻,等.干密度对击实黄土震陷性影响的试验研究[J].地震工程与工程振动,2000,20(1):75-80.
    [8]林锋,石豫川,黄润秋.高填方路基压实度不均导致路基病害机理研究[J].工程地质学报,2004,12:277-279.
    [9]孙吉主,高晖.液化条件对地表动力响应影响的有效应力动力分析[J].地震工程与工程振动,2005,25(2):150-154.
    [10]沙庆林.路基压实及压实标准[M].北京:人民交通出版社,1997.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心