客运专线铁路跨越断裂带有关问题探讨
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
研究目的:客运专线铁路安全问题备受关注。我国是一个多地震国家,地震断裂带分布广泛;客运专线铁路跨越断裂带地段存在潜在安全问题,应采取适宜的工程措施和监测方法,以确保运营安全。本文以津秦客运专线为基础进行探讨。研究结论:通过对津秦客运专线跨越卢龙断裂带地段的线路平纵断面、桥梁工程、轨道型式的分析,根据地震安评报告在无震蠕滑每年位移量不大于1 mm情况下,原设计难于适应桥梁主体结构使用寿命100年、无砟轨道使用寿命60年的要求,应采用调高量大且水平和竖向均可调整的新型桥梁支座以及适应性好且非纵连的无砟轨道,同时建立平面和竖向监测网进行动态监测。
Research purposes: The safety of passenger-dedicated line becomes a focus of all society.China is a country where earthquakes occur frequently because of the widespread distribution of seismic fault zones throughout the country.There is the potential safety problems when the passenger dedicated line passing through the fault zone,so the appropriate engineering measures should be taken and the appropriate monitoring methods should be used to ensure the security of the line operation.Taking the Tianjin-Qinhuangdao Passenger Dedicated Line as an example,this paper studies the relevant issues on passenger dedicated line crossing fault zone. Research conclusions:Based on the analyses of the horizontal and longitudinal sections of the track crossing the Lulong fault zone,the bridge engineering and the track type of the Tianjin-Qinhuangdao Passenger Dedicated Line,the original design can not meet the requirements that the service life of the main structure of the bridge should be up to 100 years and the service life of the ballastless track should be up to 60 years in light of the seismic safety assessment report stipulating that the displacement of non-earthquake creep sliding is no more than 1mm.It is suggested the new-type bridge supports with large lifting height and horizontal and vertical adjustment and the adaptable and non-longitudinal connected ballastless track should be used.Meanwhile,the horizontal and vertical monitoring network should be established to conduct a dynamic monitoring.The principle of passenger dedicated line crossing fault zone is offered.
引文
[1]铁道第三勘察设计院集团有限公司.天津至秦皇岛客运专线卢龙断裂带有关问题专题研究报告[R].天津:铁道第三勘察设计院集团有限公司,2010.The Third Railway Survey and Design InstituteGroup Corporation.Special Report on RelevantIssues of Lulong Fault Zone along the Tianjin-Qinhuangdao Passenger Dedicated Rail Line[R].Tianjin:The Third Railway Survey and DesignInstitute Group Corporation,2010.
    [2]铁道第三勘察设计院集团有限公司.津秦客运专线4个段落有砟改无砟变更说明[R].天津:铁道第三勘察设计院集团有限公司,2009.The Third Railway Survey and Design InstituteGroup Corporation.Report on the Variation fromBallast Track to Ballastless Track of the FourSegments of the Tianjin-Qinhuangdao Rail Line[R].Tianjin:The Third Railway Survey and DesignInstitute Group Corporation,2009.
    [3]中国地震灾害防御中心.津秦铁路客运专线工程场地地震安全性评价报告[R].北京:中国地震灾害防御中心,2009.China Earthquake Disaster Prevention Center.TheSeismic Safety Assessment Report of the EngineeringSite of the Tianjin-Qinhuangdao PassengerDedicated Rail Line[R].Beijing:China EarthquakeDisaster Prevention Center,2009.
    [4]GB 50111—2006,铁路工程抗震设计规范(2009年版)[S].GB 50111—2006,Code for Design of RailwayEngineering(2009 edition)[S].
    [5]TB 10621—2009,高速铁路设计规范(试行)[S].TB 10621—2009,Code for Design of High-speedRailway(Trial)[S].
    [6]GB 12897—2006,国家一、二等水准测量规范[S].GB 12897—2006,Specifications for the First andSecond Leveling[S].
    [7]DZ/T 0154—95,地面沉降水准测量规范[S].DZ/T 0154—95,Specifications for Standard Surveyof the Land Subsidence[S].
    [8]JGJ 8—2007,建筑变形测量规程[S].JGJ 8—2007,Code for Deformation Measurement ofBuilding and Structure[S].
    [9]GBT/18314—2009,全球定位系统(GPS)测量规范[S].GBT/18314—2009,Specifications for GlobalPositioning System(GPS)Surveys[S].
    [10]TG/04—2009,铁路客运专线技术管理办法(试行)(300~350 km/h部分)[S].TG/04—2009,The Ministry of Railways of thePeople’s Republic of China.The TechnicalManagement Criteria of the Passenger DedicatedRailway Line(Trial)(The 300-350km/h Part)[M].Beijing:China Railway Publishing House,2010.
    [11]铁建设[2006]189号,客运专线无碴轨道铁路工程测量暂行规定[S].Railway Construction[2006]No.189,ProvisionalRegulations on the Railway Engineering Survey forBallastless Tracks of Passenger Dedicated Rail Line[S].
    [12]黄彦彬,乔登寿,黎亚平.地震灾害对拟建兰渝铁路工程的影响及防治措施[J].铁道工程学报,2008(12):18-23.Huang Yanbin,Qiao Dengshou,Li Yaping.Earthquake Disaster Impact on Proposed Lanzhou-Chongqin Railway and Prevention Measures[J].Journal of Railway Engineering Society,2008(12):18-23.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心