摘要
根据预应力筋孔道和预应力筋的匹配要求,计算确定常用预应力筋重心偏移孔道中心的距离。在此基础上,对一孔布置6股钢绞线和12股钢绞线的两种情况,分别计算考虑和不考虑预应力筋重心偏移时预应力筋的等效荷载、综合弯矩、各跨跨中的预应力摩擦损失和总损失以及预应力引起的柱上弯矩。对计算结果进行比较分析,建议在设计有粘结预应力结构时,尤其是超长结构和宽扁结构,要考虑预应力筋重心偏移的影响。
According to the matching demand of prestressing duct's size and prestressed strands' area,deviation distances of prestressed strands are calculated.On this basis,equivalent load,resultant moment,friction loss and total loss at the middle of the span and column moment caused by prestressed strands are calculated for prestressed strands' geometry considering deviation or not.The computation is done in two cases,which are 6 strands in one duct and 12 strands in one duct.Through comparison and analysis,it is suggested that influence of prestressed strands' deviation should be considered for bonded prestressed structure, especially for bonded prestressed external-long structure and bonded prestressed wide flat structure.
引文
[1]建筑工程预应力施工规程(CECS180:2005)[S].北京:中国计划出版社,2005.
    [2]AASHTO LRFD Bridge Design Specifications[S].American associationof state highway and transportation officials.Washington D.C.,USA,First Edition,1994.
    [3]混凝土结构设计规范(GB50010—2002)[S].北京:中国建筑工业出版社,2002.
    [4]无粘结预应力混凝土结构技术规程(JGJ92—2004,J409—2005)[S].北京:中国建筑工业出版社,2005.
    [5]林同炎,伯恩斯.预应力混凝土结构设计[M].北京:中国铁道出版社,1983.
    [6]陶学康.无粘结预应力混凝土设计与施工[M].北京:地震出版社,1993.