某水利枢纽工程纵向围堰坝段混凝土温控防裂要点研究
详细信息    查看全文 | 推荐本文 |
  • 英文篇名:Study on key temperature control and anti-cracking points for concrete longitudinal cofferdam section of a water control project
  • 作者:张通 ; 周人飞 ; 李松 ; 董庆 ; 刘玉 ; 张龑
  • 英文作者:ZHANG Tong;ZHOU Renfei;LI Songhui;DONG Qing;LIU Yu;ZHANG Yan;National Research Center for Sustainable Hydropower,China Institute of Water Resources and Hydropower Research;China National Heavy Machinery Corporation;China Gezhouba Group No.1 Engineering Co.,Ltd.;
  • 关键词:纵向围堰坝段 ; 有限元仿真 ; 温度控制 ; 防裂措施
  • 英文关键词:longitudinal cofferdam section;;finite element simulation;;temperature control;;anti-cracking measure
  • 中文刊名:SJWJ
  • 英文刊名:Water Resources and Hydropower Engineering
  • 机构:中国水利水电科学研究院国家水电可持续发展研究中心;中国重型机械有限公司;中国葛洲坝集团第一工程有限公司;
  • 出版日期:2019-01-20
  • 出版单位:水利水电技术
  • 年:2019
  • 期:v.50;No.543
  • 基金:国家重点研发计划资助(2016YFB0201003);; 国家自然科学基金(51579252);; 水利部先进实用技术示范专项(011775);水利部技术示范项目(SF-201701)
  • 语种:中文;
  • 页:SJWJ201901013
  • 页数:5
  • CN:01
  • ISSN:11-1757/TV
  • 分类号:102-106
摘要
水利枢纽工程中,纵向围堰坝段作为永久性挡水建筑物,两个侧面分别具有提前挡水和长期暴露的特点,开裂风险较大,需要有针对性的防裂措施。以某水利枢纽工程混凝土纵向围堰坝段为例,采用有限元仿真的分析方法,就其过流面、暴露面温控防裂要点进行重点分析。结果表明:无温控措施时,侧面最大应力达2. 82 MPa,安全系数仅为0. 59;设置纵缝及24℃中期冷却后,过流面、暴露面最大应力分别为1. 22 MPa、1. 18 MPa,安全系数分别为1. 37、1. 41;进一步对过流侧进行25. 00 m高程以下堆渣、对暴露侧进行保温后,过流面、暴露面最大应力分别降低为0. 85 MPa、0. 71MPa,安全系数分别提高到1. 96、2. 35,均满足1. 65的设计标准。因此,对于提前过流侧面的针对性防裂措施为,设置纵缝、过流侧过流前中期冷却及堆渣;暴露面一侧由于长期暴露,易遭遇寒潮影响,其主要防裂措施为,设置纵缝、中期冷却及保温。
        Taking the longitudinal cofferdam section of a water control project as the study case,the key temperature control and anti-cracking points of its overflow surface and exposed surface are analyzed with the method of finite element simulation analysis.The result shows that the maximum lateral stress is 2. 82 MPa and the safety factor is only 0. 59 when no any temperature control measures are adopted. After arranging longitudinal joint and making the mid-term cooling at 24 ℃,the maximum stresses of boththe overflow surface and the exposed surface are 1. 22 MPa and 1. 18 MPa,while the safety factors are 1. 37 and 1. 41 respectively. After slag-piling made for the overflow side below the elevation of 25. 00 m and the insulation made for the exposed side,the maximum stresses of both the overflow surface and the exposed surface are lowered to 0. 85 MPa and 0. 71 MPa respectively,while the safety factors are enhanced to 1. 96 and 2. 35 respectively as well,and then all of them meet the design standard of1. 65. Therefore,the targeting anti-cracking measures for the in-advanced overflow side are the arrangement of longitudinal joint,mid-term cooling and slag-piling before the overflow of the overflow side,while the main anti-cracking measures for the side of the exposed surface are the arrangement of longitudinal joint,mid-term cooling and insulation due to the long-term exposure and being prone to be impacted by cold-wave.
引文
[1]李松辉,王智阳,杨莉英,等.高碾压混凝土坝裂缝成因及防治措施研究[J].水利水电技术,2017,48(1):63-66.
    [2]李松辉,李玥,孙祥鹏.水闸混凝土结构关键部位温控防裂研究[J].水利水电技术,2017,48(12):45-49.
    [3]李松辉,张湘涛,张国新,等.高混凝土重力坝关键部位温控防裂研究[J].水力发电学报,2013,32(3):181-186.
    [4]王晓峰,王洪军,王飞,等.果多水电站大坝碾压混凝土温控防裂措施[J].红水河,2016,35(4):6-11.
    [5]曾新民,马彩云,李勇,等.大藤峡水利枢纽工程布置和施工导流设计方案探讨[J].人民珠江,2013(1):46-49.
    [6]汪安华,许志安.三峡纵向碾压混凝土围堰温控设计[J].中国三峡,1997(4):15-17.
    [7]李焰,李伟丁.三峡工程混凝土纵向围堰坝身段裂缝及结构缝化学灌浆[J].红水河,2006,25(2):122-127.
    [8]柳光耀.一期导流工程坝身段混凝土裂缝成因分析及处理[J].中国三峡,2000(5):8-9.
    [9]朱伯芳.大体积混凝土温度应力与温度控制[M].北京:中国电力出版社,1999.
    [10]国家电力公司水电水利规划设计总院.混凝土重力坝设计规范:NB/T 35026—2014[S].北京:中国电力出版社,2014.
    [11]张国新.大体积混凝土结构施工期温度场、温度应力分析程序包SAPTIS编制说明及用户手册[Z]. 1994—2005.
    [12]张国新,李松辉,等.某枢纽工程纵向围堰温控复核计算[R].北京:中国水利水电科学研究院,2016.

© 2004-2018 中国地质图书馆版权所有 京ICP备05064691号 京公网安备11010802017129号

地址:北京市海淀区学院路29号 邮编:100083

电话:办公室:(+86 10)66554848;文献借阅、咨询服务、科技查新:66554700