高耸建(构)筑物爆破塌落振动峰值速度估算
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
为了研究烟囱类高耸建(构)筑物塌落触地所诱发的地震波振动速度的变化规律,利用实地量测的塌落振动数据,采用量纲分析和最小二乘法,拟合得到建(构)筑物倒塌触地振动速度的估算公式。通过实践论证表明,只要确定了塌落体的质量、质心高度,用该公式就能预测出塌落建(构)筑物到某一定距离处的振动速度。
In order to study the variation law of seism wave vibration velocity caused by collapse of high building such as chimney,the emprical formula of collapse vibration velocity was obtained with dimension analysis and least square method,based on the vibration velocity data monitored.The practice proved that the emprical formula can calculate the ground vibration velocity value of the location which is a certain distance to the collapse site of building,if the mass of collapse building and its center of mass height is determined.
引文
[1]王瑞贵,卢文波.拆除爆破中触地诱发震动的震动模型[J].爆破,2005,22(1):25-29.
    [2]周家汉.爆破拆除塌落振动速度计算公式的讨论[J].工程爆破,2009,15(1):1-4.
    [3]周家汉,金保堂,陈善良.高烟囱拆除爆破及塌落震动测量和分析[A].第七届工程爆破学术会议论文集[C],成都:2001,707-712.
    [4]吕淑然,杨军,刘国振.高大建筑物定向爆破地震振动效应检测与控制研究[J].爆破,2003,20(3):71-74.
    [5]吕淑然,胡刚,杨军.建筑物倒塌触地振动模拟研究[J].工程爆破,2002,8(3):16-20.
    [6]刘国振,吕淑然,杨军.强夯振动效应研究[J].安全与环境学报,2003,3(6):14-17.
    [7]王希之,王自力,龙源,等.高层建筑物爆破拆除塌落震动的数学模型[J].爆炸与冲击,2002,22(2):188-191.
    [8]孙金山.高耸(高层)建筑物拆除爆破倒塌过程模拟[D].武汉大学,2005.
    [9]田运生.高层建筑物爆破拆除塌落震动分析和控制[J].爆破器材,2004,33(4):25-28.
    [10]黄忆龙.爆破震动波及其传播特性研究[D].中国矿业大学,2000.
    [11]谈庆明.量纲分析[M].合肥:中国科学技术大学出版社,2007.
    [12]王迪安.79 m高烟囱拆除爆破振动与塌落触地振动对比分析[J].工程爆破,2006,12(1):86-89.
    [13]王瑞贵.建筑物爆破拆除塌落触地震动效应研究[D].武汉:武汉大学,2005.
    [14]夏卫国,倪荣福,朱立新,等.80 m高钢筋混凝土烟囱爆破拆除[J].爆破,2004,21(2):58-60.
    [15]徐泽沛.爆破拆除塌落过程及触地震动的分析研究[D].长沙理工大学,2004.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心