摘要
为了解决爆破振动监测过程中在土壤、边坡等非理想条件下的测点难于固定传感器及固定可靠度低的问题,在分析爆破振动监测固定传感器现行方法特点及现场监测需求的基础上,提出了在非理想条件下固定振动传感器的新方法——三角台法、万向台法,详细介绍了其结构、原理、操作方法、适用条件及效果分析。三角台法、万向台法在使用条件上软硬互补,解决了在绝大多数情况下的测点固定传感器的难题,和现有的粘贴法固定传感器构成了一套完整的固定方法体系,保证了振动传感器现场安放固定的可靠度以及振动数据的精确度,使爆破振动现场监测细节工作更加科学、规范。
In order to solve the problem that it is difficult to fix the sensor and the low reliability of the fixed sensor in the process of blasting vibration monitoring under the non-ideal conditions such as soil and slope, this paper puts forward the new method of fixing sensor under the non-ideal conditions on the basis of analyzing the characteristics of the current method of fixing sensor and on-site monitoring requirements. The new method including triangular pyramid platform method and universal platform method, its structure, principle, operation method, applicable conditions and effect analysis are introduced in detail; they are relatively complemented each other in terms of using conditions, which solves the difficulty of fixing sensor in most cases, and constitute a complete set of fixed method system with existing sticking method,which ensures the reliability of fixing vibration sensor and the accuracy of vibration data, and makes spot detail work of monitoring blasting vibration more scientific and standardized.
引文
[1] 国家安全生产监督管理总局.爆破安全规程:GB 6722-2014[S].北京:中国标准出版社,2015.State Administration of Work Safety.Safety regulations for blasting:GB 6722-2014[S].Beijing:China Standards Press,2015.
[2] 国家能源局.水电水利工程爆破施工技术规范:DL/T 5135-2013[S].北京:中国电力出版社,2014.National Energy Administration.Specifications of excavation blasting for hydropower and water resources projects:DL/T 5135-2013[S].Beijing:China Electric Power Press,2014.
[3] 杨年华.爆破振动理论与测控技术[M].北京:中国铁道出版社,2014:103.YANG N H.Blasting vibration theory and monitoring and control technology[M].Beijing:China Railway Publishing House,2014:103.
[4] 杨年华,林世雄.爆破振动测试技术探讨[J].爆破,2000,17(3):90-92.YANG N H,LIN S X.Investigation on blasting vibration testing technique[J].Blasting,2000,17(3):90-92.
[5] 郭汉超.槐树坪隧道爆破振动监测与控制技术[J].隧道建设,2006,26(5):47-49.GUO H C.Applied in construction of Huaishuping tunnel[J].Tunnel Construction,2006,26(5):47-49.
[6] 宗琦,汪海波,周胜兵.爆破地震效应的监测和控制技术研究[J].岩石力学与工程学报,2008,27(5):938-944.ZONG Q,WANG H B,ZHOU S B.Research on monitoring and controlling techniques considering effects of seismic shock[J].Chinese Journal of Rock Mechanics and Engineering,2008,27(5):938-944.
[7] 费鸿禄,孔祥雷.蒲石河蓄能电站下水库坝基开挖爆破振动监测[J].爆破器材,2008,37(2):1-4.FEI H L,KONG X L.Monitoring on excavation blasting vibration of lower reservoir dam foundation[J].Explosive Materials,2008,37(2):1-4.
[8] 孔祥雷,刘峰,何晓光.一种在深厚松散土层上固定爆破测振传感器的装置:CN 201620551555.X[P].2016-10-26.KONG X L,LIU F,HE X G.A device for fixing blasting vibration sensor on the deep and loose soil:CN 201620551555.X[P].2016-10-26.
[9] 孔祥雷,李娜,齐晓辉.一种在边坡岩面上固定爆破振动传感器的万向脚:CN 201720222491.3[P].2017-9-19.KONG X L,LI N,QI X H.A universal foot for fixing blasting vibration sensor on slope rock surface:CN 201720222491.3[P].2017-9-19.