摘要
为了提高单一的地质超前预报方法在隧道工程施工中对掌子面前方地质情况预报的准确性与可靠性,降低工程风险,确保施工安全,在新建铁路蒙西至华中地区铁路煤运通道三门峡至荆门段核桃园隧道施工过程中,运用地质雷达法、瞬变电磁法、TST隧道地质超前预报三种方法对隧道掌子面前方地质情况进行探测,经综合分析,较为成功的预测到岩溶和岩溶水的存在,取得了较好的效果,说明了综合地质超前预报相对于单一方法而言,更具有优越性和实用性。
In order to improve the accuracy and reliability of a single geological prospection method for predicting the geological conditions in front of the face of the tunnel engineering,reduce the engineering risk and ensure the safety of the construction,during the construction of the Hetaoyuan tunnel in Sanmenxia to Jingmen section,which is a new railway coal transport channel from Mengxi to central China. The geological conditions in front of the tunnel face were detected by means of geological radar method,transient electromagnetic method and TST tunnel advance geological forecast. Through comprehensive analysis,karst and karstic water were successfully predicted,and has achieved good results,indicating that comprehensive advance geological forecasting is more advantageous and practical than a single method.
引文
[1]王梦恕.对岩溶地区隧道施工水文地质超前预报的意见[J].铁道勘察,2004(1):7-10.
[2]曲海锋,刘志刚,朱合华.隧道信息化施工中综合超前地质预报技术[J].岩石力学与工程学报,2006,25(6):1246-1251.
[3]赵永贵,刘浩,孙宇,等.隧道地质超前预报研究进展[J].地球物理学进展,2003,18(3):460-464.
[4]肖宏跃,雷宛,杨威.地质雷达特征图像与典型地质现象的对应关系[J].煤田地质与勘探,2008,36(4):57-61.