摘要
庙沟铁矿地质条件复杂,主井井筒穿过的地层含多层富水含水层。井筒施工至-150m水平时,爆破施工后,出现突水,涌水量约120m3/h。由于排水能力不足,井筒水位迅速升至-15m标高,井内水深135m。为此,增大了井筒排水能力,降盘排水,并进行清淤作业;然后在工作面浇筑止浆垫,进行工作面预注浆,成功地治理了井筒突水。注浆后,井筒涌水量小于5m3/h,确保了井筒剩余工程、后续马头门和各硐室工程的安全顺利施工,保证了工程质量。
The geological conditions of the Miaogou Iron Ore are complex,and the strata through which the main shaft passes contains multiple water-rich aquifers.When the shaft was constructed to the level of-150 m,the water inrush occured after blast working,and the water inflow was about 120 m3/h.Due to insufficient drainage capacity,the shaft water level quickly rose to the elevation of-15 mand the depth of the water was about 135 m.For this matter,the shaft drainage capacity was increased,the hanging scaffold was dropped to drain water,and the silt-removing operation was carried out;then the grouting pad was poured on the shaft sinking face,the pre-grouting was done,and the shaft water inrush was successfully controlled.After grouting,the shaft water inflow was less than 5 m3/h,which ensured the remaining work of the shaft,the subsequent horsehead project and other chamber projects to be constructed safely and smoothly,the project quality was guaranteed.
引文
[1]王联,刘长安.井筒破碎带突水淹井分析及处理[J].建井技术,1999,20(2):8-11.
[2]辛小毛.冬瓜山千米竖井突水淹井机理分析[J].世界采矿快报,1999,15(4):23-26.
[3]曹立洲.卧龙湖煤矿主井井筒K3砂岩突水治理[J].建井技术,2006,27(5):17-18.
[4]仝洪昌.立井井筒突水淹井事故的快速处理[J].建井技术,2008,29(1):3-5.
[5]马江淮,严家平,张海涛,等.板集煤矿副井井筒地面注浆堵水技术与效果评价[J].煤矿安全,2011,42(4):45-47.
[6]柴敬,袁强,王帅,等.白垩系含水地层立井突水淹井治理技术[J].煤炭学报,2016,41(2):338-344.
[7]张向东,张建俊.深立井突水淹井治理及恢复技术研究[J].煤炭学报,2013,38(12):2189-2195.
[8]李海燕,王琦,江贝,等.深立井大水工作面注浆堵水技术[J].煤炭学报,2011,36(S2):444-448.
[9]张惠武,杨天亮,张建群.深立井大突水淹井静水抛碴注浆堵水施工实践[J].中国矿山工程,2015,44(1):45-47.
[10]唐功建,李彬,李杰.立井井筒掘进工作面岩体裂隙注浆堵水技术[J].建井技术,2009,30(2):12-13.
[11]彭帅,张鉴达,董依欣,等.秦皇岛庙沟铁矿区域土壤重金属污染分布特征研究[J].湖北农业科学,2015,54(21):5246-5249.
[12]程中平.一次爆破成巷技术在庙沟铁矿巷道掘进中的探索[J].矿业工程,2018,16(3):48-50.
[13]许雁超.庙沟铁矿露天转地下开拓工程地质勘探问题探讨[J].矿业工程,2015,13(1):7-8.
[14]周兴旺,高岗荣,薄志丰,等.注浆施工手册[M].煤炭工业出版社,2014.
[15]崔云龙.简明建井工程手册(上册)[M].北京:煤炭工业出版社,2003.