用户名: 密码: 验证码:
超大井径竖井临时改绞天轮平台布置及钢梁选择计算
详细信息    查看全文 | 推荐本文 |
  • 英文篇名:Arrangement of Celestial Wheel Platform and Calculation of Steel Beam Selection for Super Large Diameter Shaft Temporary Modification
  • 作者:许辉
  • 英文作者:XU Hui;JCHX Mining Management Co.,Ltd.Zhongnan Branch;
  • 关键词:超大井径竖井 ; 临时改绞 ; 受力计算
  • 英文关键词:super large diameter shaft;;temporary modification;;force calculation
  • 中文刊名:JZGC
  • 英文刊名:Value Engineering
  • 机构:金诚信矿业管理股份有限公司中南分公司;
  • 出版日期:2018-09-29
  • 出版单位:价值工程
  • 年:2018
  • 期:v.37;No.508
  • 语种:中文;
  • 页:JZGC201832100
  • 页数:2
  • CN:32
  • ISSN:13-1085/N
  • 分类号:250-251
摘要
竖井井筒形成贯通后,凿井期间的凿井设备及设施,已不能满足井巷工程转入井底车场及大巷掘砌的需要,必须对回风竖井进行临时改绞,以便施工后期平巷工程。
        After the vertical shaft is formed, the sinking equipment and facilities during the drilling process can not meet the needs of the tunnel engineering and the underground roadway and the main roadway. The return shaft must be temporarily modified to facilitate the construction of the later roadway.
引文
[1]简明建井工程手册[M].煤炭工业出版社,2000.
    [2]宋爱东.稳绳张紧装置在临时改绞中的应用[J].建井技术,2013,6(3).
    [3]刘耀明,秦江艳,张智山.蒙西超大直径立井临时改绞混合提升新技术[J].价值工程,2013(11).